Hi @Szilágyi Miklós ,
To update the summary task percentage based on sub-tasks in a SharePoint task list synced from MS Project, you typically need to open the project file in Project Professional. This is because the synchronization process involves refreshing the data from the project file to SharePoint, which includes recalculating the summary task percentages.
Unfortunately, there is no direct method to refresh the SharePoint task list without opening the project file. The synchronization process is designed to ensure that the project file and SharePoint task list remain linked, and this linkage requires the project file to be opened for updates.
References:
If the answer is helpful, please click "Accept Answer" and kindly upvote it. If you have extra questions about this answer, please click "Comment".