How to do forecasting and analysis for 2 sub teams within a sprint
Hi all,
I am working on a project where I have 2 sub teams teams - Front end (FE) and Backend(BE) - within my sprint team. based on capacity planning ( done on excel separately stored in sharepoint) we have different numbers of story points for each team and the sum is overall velocity of the team.
Now how can I use this information in forecasting because at the sprint level I only get the sum for sprint planning.
NOTE: I always start the title with FE and BE to identify the team this story belongs to. Can this somehow be used to differentiate teams and do analysis and planning?
Let me give example :
Capacity
FE - 14
BE - 20
total sprint velocity - 34