This is been observed that ADF activity task is getting completed but Activity status stay's IN PROGRESS , Hence subsequent activity is not starting.
Example : Copy activity - Copy started copying data from Source to Target. and JOB got completed in 2 MIN with Succeeded Message , But Copy Activity status remain IN PROGRESS for So long , Sometime we need to cancel it manually.
Seems Like there is some issue at ADF side or Integration Runtime not able communicate the message properly.