You should be aware of the following limitations if you're using the work breakdown structure in Project Operations. These limits apply to projects and tasks. For more information, see Project for the web limits and boundaries.
Field | Limit |
---|---|
Maximum total tasks for a project | 1,500 |
Maximum total duration for a project | 3,650 days (10 years) |
Maximum total resources for a project | 300 |
Maximum total links (successor only) for a project | 600 |
Maximum total custom fields for a project | 10 |
Maximum checklist items per task | 20 |
Field | Limit |
---|---|
Maximum hierarchy level | 10 levels |
Maximum links (successor + predecessor) | 20 |
Maximum duration of leaf task | 1,250 days |
Maximum duration of a summary task | 3,650 days (10 years) |
Maximum resources assigned to a task | 20 resources |
Supported date range for a task | 1/1/2000 - 12/31/2149 |
Events
Power BI DataViz World Championships
Feb 14, 4 PM - Mar 31, 4 PM
With 4 chances to enter, you could win a conference package and make it to the LIVE Grand Finale in Las Vegas
Learn moreTraining
Module
Learn about advanced project planning and task scheduling capabilities.
Certification
Microsoft Certified: Dynamics 365 Field Service Functional Consultant Associate - Certifications
Demonstrate how to configure a Microsoft Dynamics 365 for Field Service implementation to maximize tools and features available while managing a mobile work force.