Set up preferred maintenance workers

Note

Community interest groups have now moved from Yammer to Microsoft Viva Engage. To join a Viva Engage community and take part in the latest discussions, fill out the Request access to Finance and Operations Viva Engage Community form and choose the community you want to join.

During work order scheduling, you can make a preference regarding which maintenance worker or worker group is allocated to complete the work order. The use of this functionality is optional, but it can help you make a choice for the most qualified maintenance worker to complete a job, based on worker skills and competencies. Only maintenance workers that are available at scheduling time will be scheduled. If a preferred maintenance worker setup matches a work order during scheduling, but the maintenance worker is allocated to other jobs, the work order will be scheduled to another available maintenance worker.

Before you can set up preferred maintenance workers, you must first set up the maintenance workers and worker groups. For a description about how to set up maintenance workers and worker groups, see to Maintenance workers and worker groups.

Set up preferred workers

A preferred maintenance worker or worker group can be related to one or more of the following:

  • trade
  • maintenance job type variant
  • maintenance job type
  • maintenance job type category
  • asset
  • asset type

The more selections you make for the same record, the more specific your setup will be.

  1. Click Asset management > Setup > Workers > Preferred maintenance workers.

  2. Click New to create a new record.

  3. Start by creating a "default" maintenance worker or worker group. This means that you only make a selection in the Preferred maintenance worker group field or the Preferred maintenance worker field. In the screenshot below, you see an example in the first record in which "Requests" is selected as Preferred maintenance worker group.

    Note

    The default setup will be used during work order scheduling if no other, more specific, combination matches the contents of the work order.

  4. Repeat step 2 to create a new record. Make the required selections, depending on the detail level for the preferred worker or worker group.

    Example: In the screenshot below, in the sixth record, the maintenance worker Shawn Richardson is selected as preferred worker. Shawn will automatically be selected during scheduling of a work order that includes the asset "CH-BP1-03-02 and the maintenance job type "Facility assessment", if Shawn is available at the scheduled time.

    Note

    Generally, when a preferred maintenance worker is selected during work order scheduling, Asset Management goes through all Preferred maintenance workers records to check for a possible match, always checking the most specific combination first. If no match is found, the "default" record with a selection in either the Preferred maintenance worker group field or the Preferred maintenance worker field is used.

Figure 1.

You can also set up responsible maintenance workers who can be selected when a maintenance request or a work order is created. You can edit the selection in All work orders and All maintenance requests, if required. Learn more in Responsible maintenance workers.

During work order scheduling, different scores are calculated to determine which workers should complete the jobs related to a work order (those scores are set up in Asset management parameters > Work order scheduling link). If two or more preferred maintenance workers or responsible maintenance workers get the same score during work order scheduling, one worker is randomly selected. Otherwise, it is always the worker with the highest score who is allocated to complete a work order.