ProjectDataSet.TaskRow.TASK_ACT_COST Property

Task actual cost is the total current actual cost incurred for this task.

Namespace:  WebSvcProject
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

Syntax

'Declaration
Public Property TASK_ACT_COST As Double
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double

value = instance.TASK_ACT_COST

instance.TASK_ACT_COST = value
public double TASK_ACT_COST { get; set; }

Property Value

Type: System.Double

Remarks

This field may be entered or calculated.

The default value is calculated as:

ASK_ACT_COST = (Actual Work * Standard Rate) + (Actual Overtime Work * Overtime Rate) + Resource Per Use Costs + Task Fixed Cost