Change dates

Completed

With the Change Dates function, you can move planning lines on a project from one date interval to another. You can use this function if there's a delay in work or item delivery. Additionally, you can use this batch project to update currency exchange rates on selected projects. If the currency exchange rate changes and you want the updated projects to reflect the new exchange rate, this function is useful.

To access the Change Dates function, follow these steps:

  1. Select the Search for page icon in the upper-right corner of the page, enter projects, and then select the related link.

  2. Select Navigate > Project Task Lines.

  3. Select Actions > Functions > Change Dates.

Change dates demo

Watch the following video to see a demonstration of how to use the Change Dates function.