Freigeben über


Ending Time Field, Prod. Order Capacity Need Table

Specifies the ending time of the capacity need.

Running the Refresh Production Order batch job from a production order will calculate the capacity need for the special dates and time. The program uses the ending time to determine an optimal load for a machine center or a work center. For example, if the first production order has a capacity need of 6 hours on a special machine center and the normal working time is 8 hours, planning will use the remaining 2 hours for another production order and will define an ending time in the afternoon.

Tip

For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.

Parent Tables

Table Location
Prod. Order Capacity Need Table Manufacturing
Prod. Order Capacity Need Table Manufacturing

See Also

Reference

Capacity Journal