Due Date Field, Planning Component Table

Specifies the datethat this planning component must be finished.

The program automatically fills in this field with the contents of the Starting Date field on the Planning Worksheet Line table when you calculate a plan, but you can change it. If you have specified a routing link code, the program will use the starting date of the linked operation instead.

Tip

For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.

Parent Tables

Table Location
Planning Component Table Manufacturing
Planning Component Table Manufacturing

See Also

Reference

Planning Worksheet
Order Planning

Other Resources

Req. Worksheet
Calculate Plan - Plan. Wksh.
Refresh Planning Demand