Confirm, update, and send a project quotation

After you create and send a project quotation to a customer, you must get confirmation from the customer before you update the quotation status to Sent. You can update the quotation with any modifications requested by the customer. After you update the quotation status to Sent, you can't modify it. The following procedure describes the options to send a quotation for confirmation, make updates based on feedback, and then send the quotation.

Send a project quotation confirmation

You can send an existing project quotation for confirmation through email or as a printed copy.

  1. Go to Project management and accounting > Quotations > Project quotation.
  2. On the Project quotation page, select the quotation you want to send for confirmation.
  3. On the Follow up tab, in the Generate group, select Confirm.
  4. On the Confirm quotation page, set the required parameters. For example, to print the confirmation, under Print options, turn on Print confirmation, and then select OK.
  5. On the Send quotation page, select Options.
  6. On the Print destination settings page, select OK.

Update a project quotation

To modify an existing project quotation, the quotation status must be Created. Complete the following steps to update an existing quotation.

  1. Go to Project management and accounting > Quotations > Project quotations.
  2. On the Project quotations page, select the quotation you want to update. On the Action Pane, select Edit.
  3. Update the necessary field information. On the Action Pane, select Save.

Send a project quotation to a customer

  1. Go to Project management and accounting > Quotations > Project quotations, and select the project quotation that you want to send.
  2. On Project quotations, on the Quote tab, in the Process group, select Send quotation. The quotation status updates to Sent.

Note

You can't modify a project quotation after you change the status to Sent.