You can create, calculate, post, reverse, or eliminate revenue estimates. You can do this work manually or use a periodic process. This article provides information about how to work with revenue estimates for projects.
Manage revenue estimates manually
On the fixed price revenue estimate project or the Estimate inquiry page (Project management and accounting > Reports and inquiries > Estimates inquiries and reports), select Estimates.
Manage revenue estimates by using a periodic process
Go to Project management and accounting > Periodic > Estimates and select the corresponding process.
Create a revenue estimate
Complete the following steps to create a revenue estimate.
Go toProject management and accounting > Periodic > Estimates.
Select New. On the Estimate creation page, select the following parameters:
- Period code: This code determines how frequently estimates are posted.
- Estimate date: The date the estimate is processed.
- Continuous: Select this check box to create estimates only if estimates were posted in the previous period, or if the estimate is the first estimate that you created. If you don't select this check box, estimates are created even if estimates weren't posted in the previous period.
- Cost to complete method: Define how to estimate the remaining project work. For more information, see Cost to complete methods.
- Completion method: Select a completion method from the following options:
- Automatic: The completion percentage is calculated automatically and based on the cost lines included in the calculation. The cost template defines the cost lines that are included.
- Manual: The completion percentage equals the completion percentage of the last estimate. After the estimate is created, you can change the Manual calculation on the Estimates page.
- From cost template: A combination of the automatic and manual methods. This option is set automatically or manually, depending on the default value in the cost template.
- Forecast model: Select a forecast model for the estimate. You can select an estimate forecast model or a budget forecast model. For more information on budget forecast models, see Transfer budgets to forecasts.
- Print estimate list: Create and show an estimate list. The list contains the status of the current function. You can print any warnings about the estimate on the report. The following conditions cause warnings to appear in the estimate list:
- A completion percentage of more than 100 percent.
- A completion percentage less than zero percent.
- A negative amount in the To complete column.
- An estimate with no corresponding contract amount.
- An estimate with no attached cost estimate.
- Show Infolog: Select this option to receive a message that contains information about the estimate projects that the job processes.
Post WIP or accruals
After you evaluate the estimates, maintain, decrease, or increase them. You can post the WIP when you work with the Completed contract assessment principle, or post the accruals when you work with the Completed percentage assessment principle.
The estimate period status changes from Created to Posted.
Reverse WIP or accruals
Use the reverse option to credit already posted WIP or accruals, and then create estimates for the period.
Note
To reverse a period that is between other periods, reverse the necessary estimate periods and then repost them. Because all subsequent periods depend on the estimates from the previous period, don't skip any periods.
Eliminate the estimate project and finish the project
The final step in the estimate process is to eliminate the estimate project and end the fixed price project when the percentage of completion reaches 100 percent.
The following actions occur when you run the elimination:
- For a fixed price project with a completed contract, the WIP values clear from the balance accounts and post to the profit and loss accounts.
- For a fixed-price project with a completed percentage, the accruals are removed from the profit and loss accounts.
The estimate changes the status to Eliminated.
Note
In special cases, the percentage can extend beyond 100 percent. When this condition occurs, reduce the percentage of completion by using the Set cost to complete to zero method to reach 100 percent.
Reverse elimination
- Go to Project management and accounting > Periodic > Estimates > Reverse elimination.
- On the Action Pane, on the Process tab, in the Maintain group, select Estimate.
- Select Reverse elimination.
Use this page to reverse all eliminations with a specified estimate date and an estimate status of Eliminated. The transaction status changes after you select the appropriate fields.
This process also automatically changes the project status to In process if the project stage is set to finished. The estimate status of the project period changes back to Posted.