How to: Set Up Work Centres and Machine Centres

The program distinguishes between three types of capacities. These are arranged hierarchically. Each level contains the subordinate levels.

The top level is the work centre group. Work centres are assigned to the work centre groups. Every work centre can only belong to one work centre group.

You can assign various machine centres to every work centre. A machine centre may only belong to one work centre.

The planned capacity of a work centre consists of the availability of the corresponding machine centres and the additional planned availability of the work centre. The planned availability of the work centre group is, therefore, the sum of all corresponding availabilities of the machine centres and work centres.

The availability is stored in calendar entries. Before you set up work or machine centres, you must set up shop calendars. For more information, see How to: Create Shop Calendars.

To set up a work centre

The following primarily describes how to set up a work centre. The steps to set up a machine centre calendar are similar except for the Routing Setup FastTab.

  1. Choose the Search for Page or Report icon, enter Work Centres, and then choose the related link.

  2. Choose the New action.

  3. Fill in the fields as necessary. Choose a field to read a short description of the field or link to more information.

  4. In the Work Centre Group field, select the higher-level resource grouping that the work centre is organised under, if relevant. Choose the New action in the drop-down list.

  5. Select the Blocked field if you want to prevent the work centre from being used in any processing. This means that output cannot be posted for an item that is produced at the work centre. For more information, see How to: Post Production Output.

  6. In the Direct Unit Cost field, enter the cost of producing one unit of measure at this work centre, excluding any other cost elements. This cost is often referred to as the direct labour rate.

  7. In the Indirect Cost % field, enter the general operation costs of using the work centre as a percentage of the direct unit cost. This percentage amount is added to the direct cost in the calculation of the unit cost.

  8. In the Overhead Rate field, enter any non-operational costs, for example maintenance expenses, of the work centre as an absolute amount.

    The Unit Cost field contains the calculated unit cost of producing one unit of measure at this work centre, including all cost elements, as follows:

    Unit Cost = Direct Unit Cost + (Direct Unit Cost x Indirect Cost %) + Overhead Rate.

  9. In the Unit Cost Calculation field, define whether the above calculation should be based on the amount of time used: Time, or on the number of produced units: Units.

  10. Select the Specific Unit Cost field if you want to define the work centre’s unit cost on the routing line where it is being used. This may be relevant for operations with dramatically different capacity costs than what would normally be processed at that work centre.

  11. In the Flushing Method field, select whether output posting at this work centre should be calculated and posted manually or automatically, using either of the following methods.

|Option|Description|  
|----------------------------------|---------------------------------------|  
|**Manual**|Concumption is posted manually in the output journal or production journal.|
|**Forward**|Consumption is calculated and posted automatically when the production order is released.|  
|**Backward**|Consumption is calculated and posted automatically when the production order is finished.|  

> [!NOTE]  
>  If necessary, the flushing method selected here and on the **Item** card, can be overridden for individual operations by changing the setting on routing lines.
  1. In the Unit of Measure Code field, enter the time unit in which this work centre’s cost calculation and capacity planning are made. In order to be able to constantly monitor consumption, you must first set up a method of measure. The units you enter are basic units. For example, the processing time is measured in hours and minutes.
> [!NOTE]  
> If you select to use Days then remember that 1 day = 24 hours - and not 8 (working hours).
  1. In the Capacity field, define whether the work centre has more than one machine or person working at the same time. If your Dynamics NAV installation does not include the Machine Centre functionality, then the value in this field must be 1.
  2. In the Efficiency field, enter the percentage of the expected standard output that this work centre actually outputs. If you enter 100, it means that the work centre has an actual output that is the same as the standard output.
  3. Select the Consolidated Calendar check box if you are also using machine centres. This ensures that calendar entries are rolled up from machine centre calendars.
  4. In the Shop Calendar Code field, select a shop calendar. For more information, see How to: Create Shop Calendars.
  5. In the Queue Time field, specify a fixed time span that must pass before assigned work can begin at this work centre. Note that queue time is added to other non-productive time elements such as wait time and move time that you may define on routing lines using this work centre.

Example - Different Machine Centres Assigned to a Work Centre

It is important to plan which capacities are to make up the total capacity when setting up the machine centres and work centres.

If different machine centres (such as 210 Packing table 1, 310 Painting Cabin ...) are assigned to a work centre, the consideration of the single capacities of the machine centres is significant because failure of one machine centre can interrupt the entire process. The machine groups can be entered according to their capacity but may not be included in the planning. By deactivating the Consolidated Calendar field only the capacity of the work centre but not the machine centre is assigned in the planning.

If, however, identical machine centres (such as 210 Packing table 1 and 220 Packing table 2) are combined in a work centre, the consideration of the work centre as a sum of the assigned machine centres is of interest. Therefore, the work centre would be listed with zero capacity. By activating the Consolidated Calendar field, the common capacity is assigned to the work centre.

If capacities of work centres are to make no contribution to the total capacity, you can achieve this with efficiency = 0.

To set up a capacity constrained machine or work centre

You must set up production resources that you regard as critical and mark them to accept a finite load instead of the default infinite load that other production resources accept. A capacity-constrained resource can be a work centre or machine centre that you have identified as a bottleneck and would like to establish a limited, finite load for.

Dynamics NAV does not support detailed shop floor control. It plans for a feasible utilisation of resources by providing a rough-cut schedule, but it does not automatically create and maintain detailed schedules based on priorities or optimisation rules.

In the Capacity-Constrained Resources window, you can make setup that avoids overload of specific resources and ensure that no capacity is left unallocated if it could increase the turn-around time of a production order. In the Dampener (% of Total Capacity) field, you can add dampener time to resources to minimise operation splitting. This enables the system to schedule load on the last possible day by exceeding the critical load percent slightly if this can reduce the number of operations that are split.

When planning with capacity-constrained resources, the system ensures that no resource is loaded above its defined capacity (critical load). This is done by assigning each operation to the nearest available time slot. If the time slot is not big enough to complete the entire operation, then the operation will be split into two or more parts placed in the nearest available time slots.

  1. Choose the Search for Page or Report icon, enter Capacity Constrined Resources, and then choose the related link.
  2. Choose the New action.
  3. Fill in the fields as necessary.

Note

Operations on work centres or machine centres that are set up as constrained resources will always be planned serially. This means that if a constrained resource has multiple capacities, then those capacities can only be planned in sequence, not in parallel as they would be if the work or machine centre was not set up as a constrained resource. In a constrained resource, the Capacity field on the work centre or machine centre is greater than 1.

In case of operation splitting, the setup time is only assigned once because it is assumed that some manual adjustment is done to optimise the schedule.

See Also

How to: Create Shop Calendars
Setting Up Manufacturing
Manufacturing
Planning
Inventory
Purchasing
Working with Dynamics NAV