A family of Microsoft relational database management systems designed for ease of use.
How do you track progress?
I went further back, way back to a newsgroup microsoft.public.project and dug this up from 2009
When you just use % Complete, say 60%, all you are doing is telling MSP that
the tasks has say 6 days of actual duration out of 10 Days total Duration.
Since you don't tell it anything else about the task, it assumes, because it
must, that the actual start was the planned (earliest) start, and that the
task has been continuously in progress for 6 Days.
If this is not what happened, you must update with the actual facts first.
Save a Baseline
Set a Status Date
Show the Tracking Gantt View
Show the Tracking Table
Show the Tracking Toolbar
Format the Gridlines to show the Status Date as a vertical red line on the
Gantt Chart.
Type in the Actual Start Date and Actual Duration.
Do not type in % Complete. The software will calculate it for you.
Have a look at the Remaining Duration and amend it up or down if you need to
re-estimate it.
Do not leave planned duration in the past. If only 3 Days were done out of 6
planned, move the unused 3 days to the right of the status date (3rd button
on the tracking toolbar).
Do not show progress in the future. If a 10 task only started 6 Days ago, it
cannot be 80% Complete, because there cannot be 8 Days of Actual Duration
(Unless you change the Remaining Duration).