Share via

Project: change milestone % automatically when precedent % change

Anonymous
2022-12-21T18:29:46+00:00

Hi Community

Context:

I’ve a moderate complex project (~5000 tasks) for a SW development transformation project. It contains tasks from several teams, aggregated by core business  processes (eg., Customer Acquisition, order entry, billing, etc), in different systems (e.g. Web platform, back-end, integration, etc).

In this project, and for a high level management view, I’ve a section containing only milestones (e.g. SW development start, SW development end, tests start, tests end,…), having as precedents the detailed tasks from each business process / team / system.

Question:

Is there a way to automatically change the % of the milestones, as the % of its precedents change? Currently I’m doing this manually, but inevitably sometime I’ll miss one update, and then I’ll reporting incorrect progress to top management.

Thanks in advance

Microsoft 365 and Office | Project | For business | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

3 answers

Sort by: Most helpful
  1. Anonymous
    2023-02-03T02:39:15+00:00

    Alternatively, we achieve the intended outcome by creating a pseudo milestone group task.

    Create a pseudo milestone task under each core business group main task (this should be super task of all activities under that business group). Then insert a new text field (with any name) and this can be filtered to to show the progress % in each core business group. Also help to show progress across all business groups (but may not show overall project level progress but still useful to know progress group wise).

    Was this answer helpful?

    0 comments No comments
  2. John Project 49,705 Reputation points Volunteer Moderator
    2022-12-21T18:59:04+00:00

    luis.2016,

    Keep in mind that by definition a milestone is a point in time so either you reach the milestone or you don't (i.e. 0% or 100%). But to answer your question, as Dale noted, there is no automatic way to "link" completion of tasks to a milestone's completion but it could be done with a macro.

    John

    Was this answer helpful?

    0 comments No comments
  3. Dale Howard [MVP] 29,860 Reputation points MVP Volunteer Moderator
    2022-12-21T18:44:38+00:00

    Luis --

    No, there is no way to do this in Microsoft Project. You must manually updated the % Complete of each milestone task individually. Hope this helps.

    Was this answer helpful?

    0 comments No comments