PjConstraint enumeration (Project)
Contains constants that specify the type of constraint.
Name | Value | Description |
---|---|---|
pjALAP | 1 | Task occurs as late as possible in the schedule without delaying subsequent tasks. |
pjASAP | 0 | Task occurs as soon as possible in the schedule. This is the default constraint type for tasks. |
pjFNET | 6 | Task finishes on or after the constraint date. |
pjFNLT | 7 | Task finishes on or before the constraint date. |
pjMFO | 3 | Task finishes on the constraint date. |
pjMSO | 2 | Task starts on the constraint date. |
pjSNET | 4 | Task starts on or after the constraint date. |
pjSNLT | 5 | Task starts on or before the constraint date. |
Support and feedback
Have questions or feedback about Office VBA or this documentation? Please see Office VBA support and feedback for guidance about the ways you can receive support and provide feedback.