Have you checked all the SCSM jobs to ensure they are running and scheduled correctly without any failures?
MIM Reporting Incremental sync running for days
Hi MIM experts,
I've got a MIM 2016 (RTM) system with MIM Reporting enabled. This broke about 2 years ago but wasn't being used so wasn't fixed. It's now needed and I'm trying to get working again. I've got it to complete an new initial sync (took several days to migrate the 2 years worth of data to the data warehouse) and the previously failing incremental syncs now run without failing immediately. Unfortunately they run for a couple of days but don't appear to be putting any additional data into the data warehouse and then fail.
I haven't been able to find much information on the reporting component. Does anyone have some advice on where I can look to start troubleshooting this issue?
Thanks
Brett