Not all data fields from excel uploading to MS Project via the import wizard.

Edwards, Ryan 0 Reputation points
2024-10-30T14:55:14.11+00:00

I'm trying to upload a simple excel sheet to project via the import wizard.

I have two issues;

  1. Task Name does not show up when mapping to project on the wizard
  2. I have 2 columns/rows to upload - task name and duration, however only the duration will import. Why?

What am I missing?

Excel
Excel
A family of Microsoft spreadsheet software with tools for analyzing, charting, and communicating data.
1,954 questions
0 comments No comments
{count} votes

1 answer

Sort by: Most helpful
  1. Jiajing Hua-MFST 10,560 Reputation points Microsoft Vendor
    2024-10-31T03:03:40.3433333+00:00

    Hi @Edwards, Ryan

    Please make sure the workbook and sheet tab name are less than 11 characters in length and no spaces.


    If the answer is helpful, please click "Accept Answer" and kindly upvote it. If you have extra questions about this answer, please click "Comment".

    Note: Please follow the steps in our documentation to enable e-mail notifications if you want to receive the related email notification for this thread.