mgerbasioHBT --
Did you assign the Trades calendar as the Base Calendar for the resources who work the Trades schedule? If not, that is your first step to do.
Your second step is to remove the Trades calendar from tasks. This step is not necessary if you do the first step I have detailed above.
Third, when you assign resources to tasks, use the following method:
- Select a task in the Gantt Chart view.
- Right-click anywhere in the Gantt Chart pane and select the Show Split item on the shortcut menu.
- In the Task Form pane, select the name of the trades resource, enter a Units value for the resource (indicating whether the resource will work full-time or part-time), and then enter a Work value for the resource.
- In the Task Form pane, click the OK button to make the assignment.
When Microsoft Project calculates the Duration for the task, the Duration will be calculated using 8 hours as the work day. Do not fret, as the schedule for the task will be calculated correctly using 7 hour work days.
To see the correct schedule, apply the Task Usage view. For trades resources assigned to tasks, you should see the Work value in the timephased grid shows 7 hours/day (assuming the resource is assigned to work full-time).
Keep in mind that Microsoft Project calculates all Duration values using the Hours Per Day setting on the Schedule page of the Project Options dialog. The default value is 8 hours, which is why your Duration values did not correspond with the schedule of
the trades tasks. But the schedule is correct, which is all that matters. Hope this helps.