One thing we both forgot to mention is the concept of a baseline. In Project the way to keep track of the original parameters (i.e. dates, work, cost, etc.) is to set a baseline as soon as the plan is ready to execute but before it is actually started.
Baseline work represents what I believe you are calling "estimated work". Once set, the baseline does not change, unless you re-baseline. What you see in the Work field is the scheduled work. As the plan is executed and you enter values into the Actual Work field, Project will automatically update the scheduled work to equal the actual work. Project is simply updating the plan with reality. The Remaining Work field shows the work that is left based on the original scheduled work minus the actual work. The user can increase or decrease the remaining work as necessary.
I'm guessing you did not set a baseline. If you had, all the work and cost parameters (estimated, scheduled and actual) are readily available by task and by resource via the Task Usage and Resource Usage views.
Trevor will likely jump in with his ideas. Meanwhile I hope this helps.