Showing Future Tasks as "Late"

Anonymous
2020-09-03T12:41:53+00:00

Hi I have few sub tasks which are set to future dates but this set of tasks are making the summary tasks go to "Late". Even when I put the progress status as 100% and the status goes to "complete" it still shows as late. :(

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

4 answers

Sort by: Most helpful
  1. John Project 49,705 Reputation points Volunteer Moderator
    2020-09-03T14:07:02+00:00

    Victoria Cupcake,

    What is the status date? Per the Project help, a task is shown as "late" If the timephased cumulative percent complete does not reach midnight on the day before the status date, then the Status field contains Late.

    So, take a look at the Cumulative Percent Complete for each summary line (Task Usage view) and compare it to the Status Date.

    Hope this helps.

    Jonn

    1 person found this answer helpful.
    0 comments No comments
  2. Anonymous
    2020-09-04T19:48:37+00:00

    Victoria Cupcake,

    The comparison John suggests would be straightforward using a custom date field to estimate the "Complete Through" date using the formula: =ProjDateAdd([Actual Start],[Actual Duration]). 

    It's effectively the same as applying a percent complete to the task's duration.  Be sure to "Use formula" for summary tasks.  When the resulting value is less than the midnight before the Status Date, then the in-progress tasks will be marked  "Late".  (The formula generates errors for unstarted tasks; ignore them.) Good luck, tom

    0 comments No comments
  3. John Project 49,705 Reputation points Volunteer Moderator
    2020-09-04T14:13:22+00:00

    Victoria Cupcake,

    Okay, then did you compare the cumulative percent complete of the summary line(s) to the Status Date?

    Also, what version of Project are you using?

    John

    0 comments No comments
  4. Anonymous
    2020-09-04T02:39:43+00:00

    Status date was set as 03/09/2020 and I set it to 04/09/2020 and it still shows as late. :(

    0 comments No comments