Dears,
I'm struggling with an issue which I'm not able to solve.
I was able to create a dynamic gantt chart in excel using start and end dates.
However, I would like to create a more generic templates which includes generic days and weeks just to evaluate the overall effort.
I was looking for somthing with dynamic bars like a standard gantt but just wihout dates.
My intention was to specify the effor related to each specific task (like 8 days with a 5-days working week).
Could you kindly help me? Is there a way to create this kind of template?
Thank you
Kind regards
Giacomo
A family of Microsoft spreadsheet software with tools for analyzing, charting, and communicating data
Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.
Like this for each week
| WK1 | ||||
|---|---|---|---|---|
| D1 | D2 | D3 | D4 | D5 |
Thanks a lot for your kind help!
Actually I was looking for something like this:
| wk1 | wk2 | wk3 | wk4 | wk5 | wk6 | wk7 | |||
|---|---|---|---|---|---|---|---|---|---|
| Task list | effort | start | |||||||
| task 1 | 3 days | wk1 | xxx | ||||||
| task 2 | 3 wks | wk2 | xxxxx | xxxxx | xxxxx | ||||
| task 3 | 4 wks | wk1 | xxxxx | xxxxx | xxxxx | xxxxx | |||
| task 4 | 8 days | wk4 | xxxxx | xxx |
Basically, for each task you can define the effor in weeks or days and specify the starting week.
Then if possible i'm looking for a dynamic chart which shows coloured bars based on the inputs. In the example I've reported weeks but I would like to specify also days inside each week (for each week there are D1, D2, D3, D4, D5 working days). This because if a task takes partially the week, then I can better visualize the days taken to complete the activity. for semplicity, I've indicated working days with "x" but I would prefer to associate each week to 5 cells.
Does it make sense? Do you think this could be possible?
Thank you!