MS project. resource sheet, add resources to an existing resource sheet

Anonymous
2023-09-28T13:27:58+00:00

Hi,

We have a question regarding the resource sheet.

When we add more resources to the existing resource file, it will save without an error, but we will not see the names we entered, only one name mutiple times. We tried multiple times, with the same result.

Please advise what went wrong when we want to add more new resource name at a existing resource sheet. See at the end Margarida Santos Ferreira. We enter more names and her name and saved well. If we open the resource sheet again, we only see her name.

Please advise,

Regards,

Albert

Resource Name Type Material Label Initials Group Max. Units Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar Code Created Calendar GUID Unique ID
Tim Stewart Work T BS IS 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 2A222975-7704-EE11-B75E-982CBC0113E0 1
Brigit Perdon Work B BS IS 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 EC8EF513-7804-EE11-B75E-982CBC0113E0 2
Hanneke van Empel Work H BS IS 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 3x8 schedule Tue 6-6-23 C437A759-7804-EE11-B75E-982CBC0113E0 12
Abdel Chrafih Work A BS IS 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 C337A759-7804-EE11-B75E-982CBC0113E0 11
Ruben Agterberg Work R BI 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 EE8EF513-7804-EE11-B75E-982CBC0113E0 3
Bob van der Veen Work B BI 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 93A0D91D-7804-EE11-B75E-982CBC0113E0 4
Steven Loodewijk Work S BS FO 60% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 A1331524-7804-EE11-B75E-982CBC0113E0 5
Daniel Tano Work D BS FO 60% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 0AF91632-7804-EE11-B75E-982CBC0113E0 7
Dimitry Schrauwen Work D BS AFR 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 F49A0B40-7804-EE11-B75E-982CBC0113E0 8
Melanie van den Brink Work M BS AFR 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 F69A0B40-7804-EE11-B75E-982CBC0113E0 9
Marc Perlo Work M BS AFR 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 E9F81047-7804-EE11-B75E-982CBC0113E0 10
Ruben Janiuk Work R BS IRP 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 3B2B008C-7804-EE11-B75E-982CBC0113E0 13
Joey Grashuis Work J BS IRP 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 3D2B008C-7804-EE11-B75E-982CBC0113E0 14
Paul de Graaf Work P BS IRP 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 3F2B008C-7804-EE11-B75E-982CBC0113E0 15
Theo Damen Work T BS IRP 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 28B19992-7804-EE11-B75E-982CBC0113E0 16
Koen Hendriks Work K BI 10% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 A36BE02D-7E04-EE11-B75E-982CBC0113E0 17
Kim van de Braak Work K BS 10% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Tue 6-6-23 A56BE02D-7E04-EE11-B75E-982CBC0113E0 18
BAU IS Work B BAU IS 100% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Tue 6-6-23 7BE6FFFC-7E04-EE11-B75E-982CBC0113E0 19
BAU AFR Work B BAU AFR 100% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Tue 6-6-23 7DE6FFFC-7E04-EE11-B75E-982CBC0113E0 20
BAU DMVAL Work B BAU DMVAL 100% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Tue 6-6-23 C2CF4604-7F04-EE11-B75E-982CBC0113E0 21
BAU IRP Work B BAU IRP 100% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Tue 6-6-23 C4CF4604-7F04-EE11-B75E-982CBC0113E0 22
Bas Huurman Work B BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Wed 7-6-23 223F7562-0F05-EE11-B75E-982CBC0113E0 23
Depository Work D 100% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Wed 7-6-23 C084AAA1-1F05-EE11-B75E-982CBC0113E0 24
Albert Hilterman Work A BS 70% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Wed 30-8-23 30DC6375-2847-EE11-B76E-982CBC0113E0 1048584
Margarida Santos Ferreira Work JJ BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Thu 28-9-23 706915FA-305D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Thu 28-9-23 930BBA5B-315D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Thu 28-9-23 020D2E8E-315D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Thu 28-9-23 A76DAEA3-315D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Thu 28-9-23 7A5143F9-315D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Thu 28-9-23 32F1253E-325D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Thu 28-9-23 F623DD7E-325D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 70% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Thu 28-9-23 36BAC3A6-325D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 50% € 0,00/hr € 0,00/hr € 0,00 Prorated 4x9 schedule Thu 28-9-23 FF1686F8-D75D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 50% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Thu 28-9-23 D4023C07-D85D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 50% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Thu 28-9-23 7E146716-D85D-EE11-B709-C8D9D2D3F111 1048575
Margarida Santos Ferreira Work JJ BAU BCM 50% € 0,00/hr € 0,00/hr € 0,00 Prorated Standard Thu 28-9-23 09E3E62A-D85D-EE11-B709-C8D9D2D3F111 1048575
Microsoft 365 and Office | Project | For business | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

8 answers

Sort by: Most helpful
  1. Anonymous
    2023-09-28T14:02:32+00:00

    Dear Albert,

    Good day! Thank you for posting to Microsoft Community. We are happy to help you.

    As per your description, it seems that you are having issue adding more new resource name to an existing resource sheet in Project, not saved and showing up as expected.

    If the understanding above is right, to help you better, we'd like to confirm if you are having issue with Project Online Desktop client or Project Online in browser, will they encounter a similar situation?

    Does this happen to a specific project or all projects? If other users encounter a similar issue on their side in your organization?

    Meanwhile, we will also try to do test on our side to check if we can reproduce a similar situation, we will update the thread shortly once we finished testing.

    Appreciate your patience and understanding and thank you for your time and cooperation.

    Sincerely,

    Rhoda| Microsoft Community Moderator

    1 person found this answer helpful.
    0 comments No comments
  2. John Project 49,700 Reputation points Volunteer Moderator
    2023-09-29T16:17:28+00:00

    Albert,

    When you say "shared file folder" what does that mean exactly? Are the pool file and all sharer files in the same folder?

    In addition to the pool file and sharer files do you also have a dynamic master (i.e. sharer files inserted as subprojects)?

    Are all the resources in the pool file, or do the sharer files also have their own resource?

    What is the setting for sharing (i.e. pool take precedence, sharer take precedence, or some combination thereof)?

    What exactly do you mean by "amend something"?

    From the screen shot you show, it appears your are attempting to add resources via the dynamic master and not directly to the resource pool file (evidenced by the large resource Unique ID value). If so, that's your mistake.

    John

    0 comments No comments
  3. Anonymous
    2023-09-29T08:00:22+00:00

    to be clear, also when we amend something it will not appear in a proper way,

    0 comments No comments
  4. Anonymous
    2023-09-29T07:58:15+00:00

    Hi Rhodaj and John,

    We use desktop on premise (no project online, no PWA)

    We do not have sharepoint, we use a shared file folder

    We use version 2019

    To open the resource file ( open resource pool, the file is the resource pool of many projects, What do you do? we use option 2 or 3)

    What is going wrong? When we add it seems to be ok and saving and when we open again the resource sheet what we added are all the same names with the same unique ID, well we entered different names, initials and groups. We do not have a clue

    Please advise

    Thanks so far for your help,

    Regards,

    Albert

    0 comments No comments
  5. John Project 49,700 Reputation points Volunteer Moderator
    2023-09-28T15:43:04+00:00

    Albert,

    In addition to Rhoda's questions, (e.g. what version of Project are you using), is this a resource pool file with linked sharer files? If so, where exactly are you adding the resources (i.e. pool file Resource Sheet or sharer file Resource Sheet)?

    John