If I create a recurring task in Planner and set the task so that it recurs on the 31st day of each month, what happens on the months that have less than 31 days?

Is there a way to select the last day of each month on a recurring task instead?

Microsoft 365 and Office | Install, redeem, activate | For business | Other

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

Answer accepted by question author

  1. Anonymous
    2024-06-05T03:36:01+00:00

    Dear Brenda,

    The recurrence feature will automatically adjust the start date and dues date to keep the task duration if the day count of the month is less than 31.

    For example, the task is from Jan 29 to Jan 31 in 2025 with recurrence. In the Schedule view, the recurrence task in Feb in 2025 is automatically set from Feb 26 to Feb 28 and the recurrence task in Apr in 2025 is automatically set from Apr 28 to Apr 30 and so on.

    The last date can't be selected manually.

    Thank you for your effort and time.

    Sincerely

    Cliff | Microsoft Community Moderator

    1 person found this answer helpful.
    0 comments No comments

1 additional answer

Sort by: Most helpful
  1. Anonymous
    2024-06-05T20:12:45+00:00

    Thank you!!