MS Project 2010 - Physical percent complete and EVM's

Anonymous
2010-12-01T17:45:44+00:00

I am using MS Project 2010 and when I change a task to calculate Earned Value based on physical percent complete (instead of percent complete)  the earned value (BCWP) goes to 0.  Any suggestions?

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

Answer accepted by question author

  1. Anonymous
    2011-08-14T22:35:46+00:00

    The following is not a workaround instead it is just something I tried. And you can try it as follows:

    • Apply EV table to the view and insert Earned Value Method, Physical % Complete, % Complete fields.
    • Assuming you've already changed the setting to Physical % Complete in Options dialog box, just make sure it is all set to Physical % Complete for all the tasks in Earned Value Method column.
    • Overwrite all Physical % Complete cells with the original values and see whether BCWPs change or not. Pls check the timephased values as well.

    In short, I guess we need to enter Physical % Complete values after changing the settings...

    Please provide feedback whether it works or not. Pls also check this thread as well: http://social.technet.microsoft.com/Forums/en-NZ/projectprofessional2010general/thread/2907b2ad-0645-49e6-8baa-29617e760b0e

    0 comments No comments

1 additional answer

Sort by: Most helpful
  1. Anonymous
    2011-08-14T20:07:00+00:00

    Is this still a problem?

    Mike Glen

    Project MVP

    See http://tinyurl.com/2xbhc for my free Project Tutorials

    0 comments No comments