Creating Gantt without starting date

Anonymous
2012-09-14T10:11:36+00:00

Hi,

I need to create a Gantt in Project 2010 setting as start date a t0, still undefined, date. I do not want Project 2010 to show any date on the Gantt.  I already changed the grid display on Gantt to show W1, W2,..., Wn instead of dates, but near the milestones there is still displayed the milestone's date.

Is there a way to indicate to Project that the start date is still not defined and that is must show a Gantt chart relative to a generic t0 time?

Thank you.

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

3 answers

Sort by: Most helpful
  1. Anonymous
    2012-09-14T13:37:20+00:00

    Click in the timescale and then select the Format context tab.  Select Date Format.  At the bottom of the menu is an option to hide or display Task Dates.  You can also change the format of the date to show week and day.

    2 people found this answer helpful.
    0 comments No comments
  2. Anonymous
    2012-09-14T12:07:53+00:00

    You  can remove the milestone date by editing the bar style and removing the date.  Right click in the gantt chart and choose, Bar Styles.

    Alternatively, you could change the display of the date format of the milestones through formatting the layout.  Right click, choose Layout.

    Julie

    1 person found this answer helpful.
    0 comments No comments
  3. Anonymous
    2012-09-14T13:28:50+00:00

    Thanks. What do you suggest for the timeline window?