Share via

Team Planner view shows schedule conflict where there are none

Anonymous
2013-02-20T11:38:37+00:00

Team Planner view shows schedule conflict where there are none what's happening?  I have three task using a resource these task do not over lap yet it is showing a conflict what's up? Task one scheduled 8/19/13-9/27/13, Task two 10/1/13-11/8/13, Task three 4/21/14-5/28/14 I have a Standard Calender, the conflict is stated as "Resources assigned in nonworking time". Note: my resources are equipment not people.

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

10 answers

Sort by: Most helpful
  1. Anonymous
    2017-09-12T10:00:21+00:00

    I'm having the same problem as Unis_954.

    All tasks are auto-scheduled, my resources are working at 85% and 70% respectively and I can have it completely resolved of conflict. When I save and re-open I get the scheduling error for all remaining work, when NOTHING has changed. I spend hours "tricking" project to resolve it, usually by moving the tasks to unallocated then reallocating them, but whenever I resolve it, on reopening the same thing happens again.  I'm getting this in 2013, and also when I save as 2007 (my colleague is using 2007) and the same thing happens in both. It's driving me crazy - I spend all day resolving something that has no issue? I'd just ignore it but I can't as if there is a genuine error I won't see it.

    1 person found this answer helpful.
    0 comments No comments
  2. Anonymous
    2013-02-20T13:12:40+00:00

    Hi,

    A bit more detail could help.

    This resource is defined as a work resource isn't it?

    Does any one of these tasks have a Must constraint? If yes, in the Options, set a Default time format with time of day. Does it show a start of the task before the beginning of a day?

    By all means, which constraints are applied to the tasks?

    Greetings,

    1 person found this answer helpful.
    0 comments No comments
  3. Anonymous
    2013-02-20T15:02:43+00:00

    "Scheduling ignores resource calendar" is not selected.

    0 comments No comments
  4. Anonymous
    2013-02-20T15:01:45+00:00

    They are contrained as Must Start On.

    No the tasks do not start before the beginning of a day,

    and yes, it is a work resource

    0 comments No comments
  5. Anonymous
    2013-02-20T14:16:00+00:00

    Hi C.J. Cobb,

    Do you have task calendars assigned?  I have seen Project show overallocations where there are task calendars assigned to tasks and the option "Scheduling ignores resource calendar" selected.

    Julie

    0 comments No comments