Share via

Need assistance to generate S-Curve for Late Start / Late Finish...

Anonymous
2011-06-10T05:49:27+00:00

I am working as Project Planning Engineer, would like to post my first question in this forum. We are preparing S-Curve for Early Start / Late Start. I would like to generate the same directly in Microsoft Project, presently we are transfering datas & doing it Excel, it is not accurate since we can modify the data as we like. Hope it will be safe, easy & simple process to make out from MSP. I have generated S-Curve for Early Start, I need assistance to do the same for Late start.

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

4 answers

Sort by: Most helpful
  1. Anonymous
    2014-01-09T15:41:29+00:00

    There is a new product called Project Tracker that enables you to create a S Curve directly from MSP without the need for Excel. Its certainly worth a look at  www.willmer.co.uk

    Was this answer helpful?

    1 person found this answer helpful.
    0 comments No comments
  2. Anonymous
    2012-02-07T17:22:28+00:00

    Please re-post if this is still an issue..

    Mike Glen

    MVP Project

    Moderator

    Was this answer helpful?

    1 person found this answer helpful.
    0 comments No comments
  3. Anonymous
    2013-07-30T20:39:48+00:00

    Click on the Graph. The Field list shows all available options. If what you want is not there then you're out of luck.

    To get what you want I think you're going to need some VBA code. Whilst Project calculates and early and late start and finish date, it only calculates costs for the scheduled start/finish dates. Therefore there is no early and late cost over time.

    I think your macro will need to copy Early and Late start-finish to two interim custom date fields, then set start-finish to Early start dates and export timephased earned value data to Excel. Do same for Late dates and export then remove all constraint dates you just created by forcing dates and create you graph in Excel.

    Was this answer helpful?

    0 comments No comments
  4. Anonymous
    2013-07-30T17:36:07+00:00

    Hi There,

    I am producing a S-Curve using the Built in Earned Value over time report in MSP2013. How would I add a custom field to include both early and late finish on that?

    Regards

    James

    Was this answer helpful?

    0 comments No comments