Generating an S-Curve in Excel

Ajish Daniel 0 Reputation points
2024-02-06T23:41:42.8566667+00:00

How can I generate an S-Curve in Excel? I have data that includes planned and completed dates with percentage progress, and I want the graph to be an S-Curve between those dates. Blank fields indicate when there is no data available. Here is an image of the data I'm working with for better context: User's image

Microsoft 365 and Office Excel For business Windows
0 comments No comments
{count} votes

1 answer

Sort by: Most helpful
  1. Emi Zhang-MSFT 30,046 Reputation points Microsoft External Staff
    2024-02-07T06:32:53.6933333+00:00

    Hi,

    I suggest you go to Insert- Charts- insert Scatter with Smooth Lines chart:

    User's image

    Just checking in to see if the information was helpful. Please let us know if you would like further assistance.


    If the response is helpful, please click "Accept Answer" and upvote it. Note: Please follow the steps in our documentation to enable e-mail notifications if you want to receive the related email notification for this thread.