It looks like you're experiencing some issues with Microsoft Project's date calculations. I understand how frustrating that can be!
Let's break down the issue you're facing:
- Task #1 ("100% Occupancy") is dependent on Task #2 ("Lease-up begins") with a finish-start relationship, meaning Task #1 starts 8 months after Task #2 finishes.
- Task #2 starts and ends on 1/12/2029, so you expect Task #1 to start on 9/12/2029 (8 months later).
- However, Microsoft Project is calculating the start date of Task #1 as 8/24/2029, which is incorrect.
You've already checked the work week settings and time zone, which is great! Here are a few more things to consider:
- Ensure that the task durations are set correctly. Double-check that Task #2 has a duration of 0 days (since it starts and ends on the same day).
- Verify that the dependency between Task #1 and Task #2 is set correctly. Make sure it's a finish-start relationship and that the lag is set to 8 months.
- Check for any other dependencies or constraints that might be affecting Task #1's start date.
- Try recalculating the project schedule by going to "Project" > "Calculate" > "Calculate Project".
- If none of the above works, consider reaching out to Microsoft Support for further assistance.
I hope this helps, and please let me know if you have any further questions or concerns!