WRONG WEEK NUMBERS SHOWING ON MS PROJECT ONLINE
Hello
My Project start date is set as week 1 on site. Text 1 and Text 2 columns are used with formulas to show week numbers in the chart side along with in the timescale. All tasks forward of week 1 display correctly the Week Numbers in the text columns. Pre-construction tasks working back from W1 site start do not display correctly - they seem to skip a couple of weeks- hoping someone can help explain why? The holiday period is not the reason - other tasks that fall after the holiday period and before site start are also showing a few weeks incorrectly. Thanks
Formulas being used:
"W" & CStr(1+datediff("w",[Project Start],[Start]))
"W" & CStr(1+datediff("w",[Project Start],[Finish]))