WRONG WEEK NUMBERS SHOWING ON MS PROJECT ONLINE

PR 0 Reputation points
2024-09-16T15:10:00.13+00:00

Hello

My Project start date is set as week 1 on site. Text 1 and Text 2 columns are used with formulas to show week numbers in the chart side along with in the timescale. All tasks forward of week 1 display correctly the Week Numbers in the text columns. Pre-construction tasks working back from W1 site start do not display correctly - they seem to skip a couple of weeks- hoping someone can help explain why? The holiday period is not the reason - other tasks that fall after the holiday period and before site start are also showing a few weeks incorrectly. Thanks

Formulas being used:

"W" & CStr(1+datediff("w",[Project Start],[Start]))

"W" & CStr(1+datediff("w",[Project Start],[Finish]))

week numbers

Microsoft 365
Microsoft 365
Formerly Office 365, is a line of subscription services offered by Microsoft which adds to and includes the Microsoft Office product line.
4,947 questions
0 comments No comments
{count} votes

Your answer

Answers can be marked as Accepted Answers by the question author, which helps users to know the answer solved the author's problem.