Microsoft Project - Start date and task date problem and dates for same task are different in task view and calendar view

Darryl O'Donnell 0 Reputation points
2024-10-02T23:00:53.94+00:00

Hello,

I'm new to Microsoft Project desktop and am having problems with dates and the calendar.

The first problem I had run into was that I couldn't add dates for a task at any time in August 2025. I could add a date during July 2025 or September 2025, but when I clicked for XX August 2025, it would appear to work, but when I checked, it had changed the date to XX August 2024.

I thought the problem might be the project start date. I want to set the start date to 1 August 2024 (ie, prior to today's date, as some tasks from that period for this project are already complete). Again, when I go to Project/Project Information and make the change, it appears to accept the date, but when I check, it has changed to 1 August 2025.

When looking online, I saw you can also set the start date via File/Info/Project Information. At the moment, it shows 1 August 2024, even though at Project/Project Information, the date is showing as 1 August 2025.

I tried changing the start date to today's date, but then I find that the calendar shows my tasks one year from today (ie, a task that has the correct dates for 2024 in task view shows as exactly one year later, in 2025, in calendar view). I've also spotted that the calendar completely jumps a year from 1 July 2024 to 30 June 2025.

Any help appreciated!

Community Center | Discuss the Q&A site | Get started on Q&A
0 comments No comments
{count} votes

1 answer

Sort by: Most helpful
  1. Kelvin Kirby 1 Reputation point
    2024-10-03T10:38:41.01+00:00

    Hi Darryl,

    4 things for you to check :-

    1. In Options, check that your date/time format is set to show the date AND the time. This is because the default start time is 8:00 and if your calendar shows the working day starting at 9:00 (for example) this will account for a conflct.
    2. Then check that your calendar is set up correctly. As I mentioned in 1) above your working days and statutory holidays should be set here. I recommend using a calendar OTHER than the default, since the default Standard Calendar is set up as 8:00 to 12:00, 13:00 to 17:00 5 days per week with NO holidays setup. Leaving the Standard Calendar as is means you can always use that for troubleshooting and creating your own Country or Corporate calendar allows you to define the working day pattern for when the project can be worked upon. Note too that you can create additional calendars to define shift patterns for resources and also exceptions (such as night time or weekend working) for specific tasks. Make sure to base your resources on the correct calendar and also assign exceptions calendars to any relevant Tasks.
    3. Make sure auto-calculation is turned on in Options.
    4. Make sure that your tasks are auto-scheduled and not manually scheduled. Manually scheduled tasks won't necessarily move automatically.

    Hope that helps!

    Kelvin
    ******@techassoc.com

    0 comments No comments

Your answer

Answers can be marked as Accepted Answers by the question author, which helps users to know the answer solved the author's problem.