How do I make one column of random dates automatically be two weeks in advance of the first column without the dates being sequential?

Loosbrock, Jessica 20 Reputation points
2024-12-10T19:57:00.13+00:00

I have one column of dates for paystubs for my clients, and I want the next column on the right to tell me when their next paystub is paid (in two weeks).

I will update the first column myself because this is the last paystub I have received from them. Then, I want the next column to update based on what I enter, two weeks ahead of the date I input.

I cant figure out how to do this because these dates are not sequential. They are all different.

(This post also MADE me pick a tag that is totally irrelevant, I dont get it....)

Microsoft 365 and Office | Excel | For business | Windows
Microsoft Security | Intune | Configuration Manager | Updates
{count} votes

Answer accepted by question author
  1. Barry Schwarz 4,871 Reputation points
    2024-12-11T06:04:19.9333333+00:00

    If we assume the dates you input are in A1:A10, then

    • Enter "=A1+14" (without the quotes) in cell B1.
    • Copy B1 to cells B2:B10

    Whenever you update the date in a cell in column A, the corresponding cell in column B will automatically adjust to the date 2 weeks later.

    1 person found this answer helpful.

1 additional answer

Sort by: Most helpful
  1. Loosbrock, Jessica 20 Reputation points
    2024-12-11T15:46:40.4266667+00:00

    Thank you! I am so new to this. It worked great!

    0 comments No comments