==>How about phase 3 & 4 ? Is the deferral still based on # 1 or is it sequential, or 3 is based on 2 and 4 is based on 3?
Based on my experience, every phase is based on the success of the previous phase, so phase 3 is based on phase 2, and phase 4 is based on phase 3. For the manually configured multiple phases, we should correctly configure below two settings:
- Criteria for success of the previous phase
- Conditions for beginning this phase of deployment after success of the previous phase