Handling Baselines

George vanderwerk 1 Reputation point
2021-05-07T07:27:46.347+00:00

Hi,
I do not often use Project. The available help only states how to set a baseline and that one can set eleven baselines. It also states that one can compare baselines, but does not explain how to.

Yes I can set eleven baselines. But the program does not show where they are stored.
When I open a comparisation view it only shows current and baseline 0

  • How can I open and view a baseline (1 upto 11) I have made ?
  • How can I open and view more than one baseline (1 upto 11) in 1 sheet?
  • How can I CHOOSE one or more baselines?
  • And how can I add this or these to the current project?

It is probably very basic........ but I can't find the answers in the program.
My version is 2013.

Can anyone please explain me every step?( As my version is in Dutch I would have to translate everything and incomplete steps will get me off the rails.)
Thanks.

Not Monitored
Not Monitored
Tag not monitored by Microsoft.
37,795 questions
0 comments No comments
{count} votes

1 answer

Sort by: Most helpful
  1. Deva-MSFT 2,256 Reputation points Microsoft Employee
    2021-05-11T17:13:32.173+00:00

    Unfortunately Microsoft Project is not supported here; please use the tech community.

    0 comments No comments