Sharepoint/Microsoft Project Integration Notifications Based on Dependent Tasks

Pipe, Matthew 21 Reputation points
2021-06-02T14:45:14.537+00:00

I am looking to put together a SharePoint/Project integration plan and am looking for the ability to notify a user their task is ready based on their predecessor being completed

Is this a possible action?

Microsoft 365 and Office SharePoint For business Windows
0 comments No comments
{count} votes

Accepted answer
  1. JoyZ 18,111 Reputation points
    2021-06-03T06:01:58.923+00:00

    @Pipe, Matthew ,

    We could sync with SharePoint tasks list from Project Professional, some default fields will be mapped, such as % Complete.

    Then we could create a 2013 workflow based on the task list(Since the task list is a classic app, so Power Automate is not available) , if %Complete equals 100%, send email to users.

    101918-image.png

    Start Options:

    102002-image.png
    More information for your reference:

    https://learn.microsoft.com/en-us/office/troubleshoot/project/sync-with-tasks-from-project

    https://support.microsoft.com/en-us/office/sync-with-a-sharepoint-tasks-list-fb956d2c-723d-4d5a-b7e5-710ef82aa27a?ocmsassetid=ha102828524&correlationid=9a5e8f8f-c6a0-4255-938c-3d7cefaf4849&ui=en-us&rs=en-us&ad=us


    If an Answer is helpful, please click "Accept Answer" and upvote it.

    Note: Please follow the steps in our documentation to enable e-mail notifications if you want to receive the related email notification for this thread.


0 additional answers