Hi,
Just to clarify if necessary.
DURATION of a summary task is not cumulative. It is the time between the start of the first task and the finish of the latest. When there are say two 4 hour meetings this morning 8-12 which you have under a summary task, duration of that summary task will be 4 hours as you have sen, because there is no activity below that summary task before 8 this morning and none after 12 noon.
But suppose the second meeting is rescheduled to next week Tuesday morning (which in Project you can plan through a constraint) then duration of the summary task will be 5,5 days (although sum of duration is 1 day).
Hope this helps,