Hi Jan, thanks you for your reply.
Can you help me clarify another thing below -
The only change I made from the original baselined plan was added some new tasks and their predecesors, then baselined the plan again.
Could that be the cause? I just don't see how I could entered actual work at a date that is later than the finish date, all my project tasks are driven by the predecesors.
In the task usage view, I see even weird dates in the right side of the calendar like window, the tasks in question are fall into year 2013, I have no idea where that is coming from. My project end date is October 2012.
Below is an example: an 8 hour task run from 8/6 to 8/14 under auto schedule.
| Task Name |
Work |
Duration |
Start |
Finish |
| Modify Costco Fix |
8 hrs |
1 day |
Mon 8/6/12 |
Tue 8/14/12 |