Share via

Summary task % complete is wrong

Anonymous
2013-03-06T21:06:11+00:00

I have Microsoft Project 2010.  In my project plan, all tasks are 100% complete and all milestones are 100% complete, yet the % Complete for the Summary task is at 99%.  All of the task dates are in the past.  Is this a bug?

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

3 answers

Sort by: Most helpful
  1. Anonymous
    2013-03-07T14:27:34+00:00

    I have had issues in the past with summary task % complete not updating, but I cannot duplicate now.  As an experiment, take one of the milestone (zero duration) tasks and change the % complete to something other than 100%.  Does the summary task % complete change?  Set it back to 100% - any better?

    Take a look at the tracking table - do all tasks have an actual finish date?  Does pressing F9 fix it?

    Was this answer helpful?

    0 comments No comments
  2. Anonymous
    2013-03-07T04:46:18+00:00

    It says SP1 MSO (14.0.6129.5000).  I didn't filter, but I displayed the Status column as well as the % Complete column and all of the tasks were Complete.

    Was this answer helpful?

    0 comments No comments
  3. Anonymous
    2013-03-06T21:12:10+00:00

    I'd run a quick filter for all incomplete tasks.  The Project summary task should be updating if all subtasks are 100% complete.

    What service pack is installed to project 2010?

    Julie

    Was this answer helpful?

    0 comments No comments