By default the week days in MS-Project are from Monday to Friday, and, Saturday, Sunday are shown as non-working days.

I need to change the work days from Sunday through Thursday, and the weekends to be Friday & Saturday.

How can I do this for all new projects ?

Thanks

Sena

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

Answer accepted by question author

Anonymous
2012-08-24T07:37:10+00:00

Hi,

  1. Open any project (may be an empty one)
  2. Project ribbon, change working time button
  3. Click Work Weeks, then Details
  4. For Friday, click Non Working time; for Sunday, click Set day(s) to these specific Working Times, enter the Sunday working times, Enter, OK
  5. FIle, Organizer, Calendars tab: Copy the Standard Calendar into Global.mpt

There you are.

Greetings,

Was this answer helpful?

0 comments No comments

1 additional answer

Sort by: Most helpful
  1. Anonymous
    2012-08-24T20:11:41+00:00

    Many Thanks ! ....... that was perfect :)

    Was this answer helpful?

    0 comments No comments