I have a task that only has cost resource defined -- basically to track the occurrence of a large purchase. It is well before the status date. It has been marked 100% complete. However, the ACWP is showing up as negative! The figures are as below:
PV (BCWS) = $205.76
EV (BCWP) = $2,324,664.41 (this was also $205.76 until I used the option of EV based on physical % complete and marked the physical % complete as 100%)
AC (ACWP) = ($2,447,026.00)
Cost = $2,324,870.17
Actual Cost = $2,324,870.17
Baseline Cost = $2,324,664.41
Fixed Cost= ($2,447,026.00) (calculated internally by MSP)
How do I get the right numbers --- that is, PV=Baseline cost, and AC = Actual Cost? As one can guess, the numbers as they are now render the EV graph totally useless with EV, PV, and AC lines going in totally different directions!