A family of Microsoft relational database management systems designed for ease of use.
Louis,
First of all, do you have SP3 installed? If not, install it.
You may or may not get a warning message depending on how the data is entered. For example, if I set up a 5 day task with zero hours work and then use the Assign Resources window to assign a resource at 100%, no warning message. But, if I first enter 40h in the Work field and then try to assign a resource at a unit value less than or greater than 100%, an error message, similar to the one you see, appears. However, assigning the resource at 100% with 40h in the Work field gives no warning message.
The main point is this. Project's work equation is:
Duration = Work/Units
If duration is fixed, then you can enter either work or units and Project will calculate the remaining parameter.
Hope this helps.
John