Share via

MS Project not recognizing excel date format

Anonymous
2014-10-07T23:59:26+00:00

Trying to work this one out - thinking that the answer must be obvious but no matter what I try I can't seem to resolve it....

I have this excel spreadsheet (.xlsx if that makes a difference) that I'm opening up in Project by mapping the task data.

I map the scheduled start and finish dates to the start and finish fields in project respectively.  But project seems intent on displaying the date fields as text using the general format in excel. 

Any thoughts?

Thanks

Matt

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

5 answers

Sort by: Most helpful
  1. Anonymous
    2014-10-24T21:11:07+00:00

    Thanks for the update, Matt.

    Was this answer helpful?

    0 comments No comments
  2. Anonymous
    2014-10-24T04:38:02+00:00

    Hi Julie,

    Thanks for the response - I decided to go with the macro option and eventually managed to get it doing what I wanted it to do...

    Cheers

    Matt

    Was this answer helpful?

    0 comments No comments
  3. Anonymous
    2014-10-08T11:41:23+00:00

    It certainly didn't take me long to find the other thread :-)

    Was this answer helpful?

    0 comments No comments
  4. John Project 49,710 Reputation points Volunteer Moderator
    2014-10-08T02:20:23+00:00

    Julie,

    This question almost seems like deja vu all over again :-)

    John

    Was this answer helpful?

    0 comments No comments
  5. Anonymous
    2014-10-08T02:15:03+00:00

    Hi Matt,

    See:

    http://social.technet.microsoft.com/Forums/projectserver/en-US/61a509a5-ce9c-4602-872c-7c3b522b70d3/excel-import-of-dates-while-in-manual-task-mode?forum=projectprofessional2010general

    for a discussion of Project and manually scheduled tasks.  Although the thread is about Project 2013, you may be having some similar issues with Project 2010.

    Was this answer helpful?

    0 comments No comments