Angelo --
What happens if you try filtering WITHOUT hiding the Project Summary Task? Does that work? Is this happening on all projects or only one project?
If you only have this problem on one project, ne thing you might try the following:
- Display the Gantt Chart view in the project.
- Display the Project Summary Task.
- Click the Task ribbon tab.
- Click the Gantt Chart pick list button and select the Reset to Default option.
- Click the Yes button to reset the Gantt Chart view back to the default settings.
The reason I suggest the above steps is because I was getting "wacky" behavior with the Gantt Chart view in one particular project, where applying a highlight filter did not highlight any rows. After resetting the Gantt Chart, the project now works perfectly. Just a thought. Hope this helps.