I am trying to update the tasks by using Update Project.
In the popup I select the 'Reschedule uncompleted work to start after' and I select today's date: Jan 8, 2015
I do this only for one selected uncompleted tasks which has Do not start before March 10, 2015.
When I press OK I get the message: 'project did not rescheduled certain unstarted tasks because of constraint date applied to them ... (with the whole explanation).
The actual result of me pressing OK for this task should be: Nothing. Nothing, since the task is scheduled in the future. Yet this task, in my true project schedule, prevents me from updating all of my project. And yes I could select the tasks that do not
have a 'must start' constraints and yes I could probably use something else than 'must start' but to me, that would be a workaround something that should work.
I've done this before, not in this version as we have just received it. I have to be missing something.
Thank for your help.