Please help with Project 2013 issue with formating bars. With previous versions I could highlight all the tasks in the task column and format all the bars to show the bar ID. With 2013 when doing this only the bards visible on the screen have the ID added. Then when I scroll down and try to add the ID to these bars it looses those previously marked with the ID. Similar issues with formating bar style and colours. The only was I can find around this problem is to change each task individually. On a large programme this takes ages.

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

7 answers

Sort by: Most helpful
  1. Dale Howard [MVP] 29,860 Reputation points MVP Volunteer Moderator
    2013-10-09T14:27:16+00:00

    Paul --

    Because you manually applied formatting to some or all of the Gantt bars, your manual settings will override the settings I had you try in the Bar Styles dialog.  To fix the problem, try this with the Gantt Chart view applied:

    1. Click the Task tab to display the Task ribbon.
    2. Click the Gantt Chart pick list button and select the Reset to Default item on the menu.
    3. When prompted to reset the Gantt Chart view, click the Yes button.

    Completing the preceding set of steps will reset the Gantt Chart settings to their default.  Now, you should be able to use the Bar Styles dialog to format the Gantt bars the way you want for every task.  Hope this helps.

    Was this answer helpful?

    6 people found this answer helpful.
    0 comments No comments
  2. Anonymous
    2013-10-09T14:39:19+00:00

    Dale,

    OK. Thank you

    Was this answer helpful?

    1 person found this answer helpful.
    0 comments No comments
  3. Dale Howard [MVP] 29,860 Reputation points MVP Volunteer Moderator
    2013-10-09T13:14:17+00:00

    Paul --

    Double-click anywhere in the white part of the Gantt Chart pane to display the Bar Styles dialog.  Using this dialog, you can format all Gantt bars of a particular type simultaneously.  Select the Task item in the first row, and then click the Text tab in the lower left corner of the dialog.  In the Text section, you can display the ID number of each task to the left, right, top, bottom, or middle of the Gantt bars.  Hope this helps.

    Was this answer helpful?

    1 person found this answer helpful.
    0 comments No comments
  4. Dale Howard [MVP] 29,860 Reputation points MVP Volunteer Moderator
    2013-10-09T16:06:32+00:00

    Paul --

    So, did this solve the problem?  Let us know and we will try to help.

    Was this answer helpful?

    0 comments No comments
  5. Anonymous
    2013-10-09T13:30:43+00:00

    Dale,

    Thanks for your reply. Unfortunately I have tried this but it doesn't fix the problem.

    Was this answer helpful?