When I display the resource usage sheet at the moment, and open a particular resource's tasks, it will shows those tasks with no context. My project schedule has five different workstreams in it.
I have to produce a regular report which shows my forecast FTE usage, broken down by resource, per month, per workstream.
Each workstream is of course a summary task within my schedule. Is there any way to create a view to show this information. My report looks something like this:
Workstream 1
April May June July
Joe Bloggs 20h 25h 19h 7h
Fred Smith 18h 19h 4h 12h
Workstream 2
April May June July
Jane Bloggs 16h 18h 8h 17h
Freda Smith 8h 10h 6h 12h