Tasks spanning multiple days

Anonymous
2013-09-18T19:36:09+00:00

I'm converting from 2007 to 2010.  I was reading that I can now find project information to input Start dates under: File-> Project Information section.  If I enter a task and put a 1 wk duration, it will show starting/finishing, i.e. Monday - Friday.  However, if I need to update the start date to start at a later date using the above instructions ("Start Date" under Project Information in the File menu), it changes my schedule to Monday - Monday.  The only way to get it corrected is to go to Project->Project Information to change the start date there instead.  Why does the Project Information section under the file menu cause the tasks to span across days?

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

3 answers

Sort by: Most helpful
  1. John Project 49,710 Reputation points Volunteer Moderator
    2013-09-18T22:51:58+00:00

    Shaunda,

    Go to File/Options/General group. Pick a date format that includes the time.

    As an update, I did confirm this issue with another experienced user. I will report this as a bug to Microsoft although since it is a minor issue and there are better ways to set the Project start date,  I wouldn't hold out any hope for a fix.

    Further update: I did get confirmation of a bug in Project 2010 and as I understand it, the same problem also occurs in Project 2013. The bottom line is use the standard method for setting the Project Start Date.

    John

    Was this answer helpful?

    0 comments No comments
  2. Anonymous
    2013-09-18T21:49:29+00:00

    Thank you!  I was thinking it must be changing start time somehow but couldn't figure out how to display time.  How do you see the time schedule?

    Was this answer helpful?

    0 comments No comments
  3. John Project 49,710 Reputation points Volunteer Moderator
    2013-09-18T21:08:12+00:00

    Shaunda101,

    It looks like a bug to me; I'm attempting to confirm it. The reason the task finishes on the following Monday when you set the Project start date via File/Project Information is because it incorrectly sets the start time to 2:00 pm instead of the default 8:00 am.

    Until I can confirm whether it is a bug, set the Project Start date via Project/Properties group/Project Information.

    John