Logios --
No, the date limits you describe are hard dates that you cannot change in Microsoft Project 2010. In Microsoft Project 2013, however, Microsoft has changed the latest possible date to December 31, 2149. However, there has been no change to the earliest possible date, which is January 1, 1984, as you describe. Thus, I think you will need to live within these limits. Hope this helps.