A family of Microsoft relational database management systems designed for ease of use.
Pardon me for bumping in.
The first part of the error message:
"This over allocation can't be resolved." Anat" is assigned at more than the resource's maximum units task…Either reduce this resource's assigned units or increase the resource's resource availability in the resource information dialog box."
indicates that Anat is assigned at above 100% to a single task. This may occur if you have used Fixed Duration or Fixed Work tasks. Add the Peak field to the Resource Usage view (left side) to see if you have the resource assigned at above 100%
The second message may be occurring if you are attempting to level resources and have the option "Level only within available slack" selected. With that option selected, Project cannot fix an overallocation if it cannot delay a critical task. Try unchecking that option and level Anat again.