Resource Sheet with "Resources - Work" Filter applied does not show the correct amount of work as assigned in the tasks

Anonymous
2014-10-01T21:59:35+00:00

I am attempting to apply the filter, "Resources - Work" on a report and on my resource sheet. When I do so, it is showing "incorrect" values for the work field. In the first image, I show the assignments and associated work on my gantt chart - I have highlighted the amount of work. In the second image, you'll see how much "Work" is reported from the resource sheet(which should be a summary), in this case "0" hours.

Any help is greatly appreciated.

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

11 answers

Sort by: Most helpful
  1. Anonymous
    2014-10-10T13:44:41+00:00

    Sorry for the delay in replying.  

    thanks for the information that you are working with a resource pool.  When you see the issue in the Resource Sheet view, are you:

    • Working in the Resource Sheet view in the pool file OR
    • Working with the Resource Sheet view in a sharer file?
    • If you are working with the sharer file, do  you have the pool file open?

    How log as the resource pool file been in use?  It may be time to re-build the pool.  Have you "audited" the pool lately to ensure that all connected files are accurate?

    Was this answer helpful?

    0 comments No comments
  2. Anonymous
    2014-10-07T16:16:31+00:00
    • I am using a shared resource pool
    • Project 2013 Professional
    • Service Pack 1 has been applied
    • No project Server
    • Yes - the hours show as expected
    • I am definitely willing to share this file via email.

    I am new to the community, and quickly looked to see where I can email you, but cannot find it. Can you give me guidance on contacting you?

    Was this answer helpful?

    0 comments No comments
  3. Anonymous
    2014-10-07T00:11:30+00:00

    This is truly odd.  A couple of extra questions:

    Are you using a shared resource pool or are the resources in the same project file?

    What version of Project?

    What service packs are applied?

    Are  you using Project Server?

    If you create a new file with one resource and two tasks, and assignments - do the work hours show as expected?

    Is this a file you can share via email?

    Was this answer helpful?

    0 comments No comments
  4. Anonymous
    2014-10-06T19:42:50+00:00

    Hi Julie, thanks for the reply!

    The correct hours DON'T show up in the resource sheet if I don't apply a filter. However, if I go to my Resource Usage view, all the times show up correctly.

    I increased the height of the header row to include the full text. Work is "Work", not Work variance.

    Was this answer helpful?

    0 comments No comments
  5. Anonymous
    2014-10-03T12:47:47+00:00

    Do the correct hours appear in the Resource Sheet view if you don't apply a filter?  Any change the "work" field you see in the view isn't the work field but perhaps Work Variance?  Increase the height of the header row - the "Material" field you show is actually Material Label.

    Was this answer helpful?

    0 comments No comments